especially when using the shorter channel version. Elegant chrome channel covers with an integrated height adjusting system.
Waterproof tanking solution for wetroom on a wooden and concrete floor
Interested in new wet room but don’t know how much would it cost? We have prepared few standard layouts for you the get rough estimate. For more precise prise please arrange no obligation onsite visit. Alternatively add to the shopping basket and place an order. Still no obligation.






All wet room trays slope to a central or offset drain. Once installed the bathroom can be tailed the normal way. These waterproof trays and directly tile-able units allow water to drain away through a narrow gap between the cover plate and tile surface covering. Kits are equipped with polished stainless steel version, a brushed stainless steel.
Walk in shower systems are suitable for installation in concrete or rigid suspended wooden floors. The board is installed instead of plasterboard or wooden sheet and is simply screw fixed directly onto wooden stud-work or brick/block work. When used to level uneven walls, it delivers the finished job much faster than rendering or plastering. There is minimum dust even when drilling.
Tanking solution slope to a central or offset drain
Once installed the wet room can be tailed the normal way. These trays prefabricated and directly tile-able units allow water to drain away through a narrow gap between the cover plate and tile surface covering. Kits are equipped with polished stainless steel version, a brushed stainless steel.
Wooden floor or concrete with brushed stainless steel finish
Wet room fitting services include waterproof tanking solution on a wooden floor used by Mogio are complete series different performed Aqua Boards suitable to create a wet room on a wooden floor as well as on concrete.
Tanking boards can’t be thinner than 3 cm
Another important issue in the performance of the shower without shower tray is to ensure waterproofing and waterproof where the tanking boards can’t be thinner than 3 cm. Using the waterproof matts are not recommended for floors as protection should be applied against durability, flexibility and movements, and only special board can provide such assurance. Different tanking methods can be mixed together i.e. matts for walls and panels for floor. Complementation of either solution should contain tapes and O-rings and bituminous coating. All corners, drains should be fitted and sealed with a special kind of silicone, which characterizes by high flexibility and is resistant to mold. The continuity of the insulation will provide a sealing strip which lies at the corners.
Bubble free solution floor level showers featuring a fitted in sealed floor drain a supplementary waterproof coating and a predefined slope that require fat less work on and building site and save the wet room fitting specialist a lot of time. Let’s demonstrate installation of the wet room drain with horizontal drain. Put down edge insulating strip to avoid creating an acoustic bridge.
Tanking for use in new builds and renovations
High system security with manufacturer’s warranty
- Wide variety of design, function and size
- Customisable without any invalidation of warranty
- Precise predefined slope
- Accessible and able to take the load of a wheelchair
- Adjustable height for a variety of tile thicknesses
- Drainage very simple to clean
Wet room advice on key measurements
We are happy to visit you in London and provide free advice. Save the wet room fitting specialist a lot of time. Installation with a horizontal drain, will be demonstrated here:
– height of more than 7 cm of trap to allow cleaning it from the top
– flat trays have only 2 to 4 cm deep to flush properly either to middle or linear
– the whole wet room solution should be not more than 15 cm, measured from the bottom of the trap to the surface
– the pipe has to have a diameter of about 50 mm and can not be shorter than 0.5 m, which allows freedom of movement to
– proper slope towards the drain, which may not be less than 2%.
– spraying can not be away more from plumbing than 1-1.5 m
– do not forget that position of drains should prevent flooding the bathroom by flowing water. Please consider step tile which protect against uncontrolled flotation of water outside the shower.
Check the dimension, position and gradient
Install the base element in a dry condition and mark out the position of drain. Pipe can now be modified to the required length and drain can be mounted. Before the filling process put the protective cover in place so that no dirt ends up in the drain. The opening is filed to the right height with the bonded leveling compound.
Check the dimension and smooth to the required height. Before the wet room floor is placed in the correct position once again confirm that everything is okay. Remove the protective over and place element once again in the correct position for confirmation if it does fit properly. If doesn’t fit, now is the time to correct the position at the drain. Now, fit the seal ring from above into the plastic frame channel and screw down the shower base with the seal insert, tighten it manually once again.
It’s important that the thin layer mortar covers all the underside of the element. First apply a concat layer BB610 to the sides which will be places against the wall with the building boards and the element is inserted flash into the recess. Check the evenness have the installation using a spirit level. Ten seal the joins ad the tray element tot he walls using bb10 yet again and then smoothing trowel.
Allow the tile adhesive to cure for at list 12 hours
Allow the tile adhesive to cure for at list 12 hours under a little pressure for example with the help of tile bundles. Once the tile adhesive is heartened sufficiently the isolating script can be cut tot he correct height. A base structure for wash basing can be easily created from building board. Seal shower board, wall boards with primo and screed. the joining surface can be sealed using a dry flex or flexible waterproofing grout. Once the sealant has hardened after about five hours tiling can commence.
This is simple guide to installing underfloor heating system, warm matt.
Before starting please read the manual in in your warm matt pack.
Before you start, measure the area you will be working in to go to the right number of packs for the rooms. Cheerfully work out the working area, excluding any furniture or fittings.
Required:
Installation boards to improve energy efficient for about 15% saving money and heating rooms up to 10 times faster. Make sure the floor service is clean and dry. With the trowel we can stick board with flexible tile adhesive on to the floor. Lay the board and press firmly, stuck up all the joints in the brick fashion. The boards can be easy cut in situation when you have to fit to exact shape. On wooden board, you can also screw the isolating board to wooden boards. If the floor should be prepared with the primer, leave it to dry.
Under floor heating is recommended for wet room floors
The thermostat adjust to the temperature inside, and start automatically when the temperature goes down. Intelligent sensor enable thermostat controls your environment based on the setting you have entered. Internal built in management feature let you to monitor usage of the heating and save money by reduction g unnecessary energy consumption it will help you determine the ideal temperature setting for your house. Mogio can provide installation of many different brands but this one let you to save on average 20% with your trade discount. Mogio also provide free advice during installation and during the maintenance.
Double check if you have correct heater to fit the required space, check the wire spaces. Check the system with the digital meter. It is important to test before, during and after installation. Check the manual for more details. Marks start point close to power supplies no more than 2.5 meter away. If more than 2.5. You should consider junction box. The heater should be laid no closer than 4cm from the wall. Minimum gaps should be 15mm between the wires.
In manual there should be layout chart. Remember the wires should never cross! To layout the heating wire, you should start from the closest point to the electric point.
Follow all points you marked and lay down the wire being careful not to go to close to the wall and avoid fittings, furniture, bath, walk in shower tray (under floor heating is recommended for wet room floors). Secure the wire with tape to keep the positions and achieve even positioned. Heating matt allows you to adjust the layout to provide best heating experience. Once you completed the whole layout now you will be able to connect the temperature sensor and thermostat
Heating, plumbing should be undertaken by qualified professionals
Underfloor heating must be wired with RCD and should be undertaken by qualified electrician. Mogio can provide also installation certificate.
You can chisel out the sensor between the panels if required but must be positioned between heating wires. Tape the sensor down to the isolating boards. At the stage you should check again the test of the wires to make sure nothing has been cut or damaged during the preparations. Before you start tiling check the wiring state and make sure that the tile adhesive is flexible, and do not damage heating wire with the trowel. Use enough the adhesive fully under the tiles. Do not clean the grout lines with utility knife because you can damage, cut the heating cable. Leave the floor to set for at least 5 days to allow the adhesive to fully dry, then enjoy the luxury of underfloor heating.